1973-4994rRESOLUTION NO. 4994
RESOLUTION DETERMINING LOWEST RESPONSIBLE BIDDER AND
AWARDING CONTRACT FOR TAFT PARK BUILDINGS
CITY PROJECT NO. 653
BE IT RESOLVED by the City Council of the City of Richfield, Minnesota
'as follows:
1. That it is hereby determined that the bid of Keho Construction
Company is the lowest bid by a responsible bidder for the construction of
a neighborhood building and a control center building for Taft Park,
City Project No. 653.
2. That the bid of Keho Construction Co. for the construction of the
above referenced project, at the price contained in their proposal of
May 24, 1973, with an estimated construction cost of $82,800 is hereby
accepted.
3. That said proposed contract for the construction of said city
project is hereby approved and adopted and the Mayor and Manager are hereby
authorized and directed to execute said contract for or on behalf of
the city of Richfield and the Clerk is authorized and directed to affix
the city seal thereto.
4. That payments to be made under the terms of said contract shall
be charged against the Construction Fund.
5. That the Corporate Surety Bond in the sum of the estimated
contract price which accompanies said proposed contract is hereby accepted
and approved.
6. That the City Clerk is authorized and directed to return the
security documents to the unsuccessful bidders upon the execution of said
proposed contract.
Adopted by the City Council of the City of Richfield this 29th
day of May, 1973 .