1970-4347r~ .- ,
~~
RESOLUTION N0. 4347
RES01';UTION ORDERING PREPARATION OF REPORT ON STORM SEWER CONSTRUCTION
EAST 71ST STREET, 4TH AVENUE TO 3RD AVENUE
EAST '71ST STREET, 3RD AVENUE TO 57'EVENS AVENUE
EAST 72ND STREET, 3RD AVENUE TO STEVENS AVENUE
EAST 73RD STREET, 3RD AVENUE TO 5TH AVENUE
EAST 74TH STREET, 2ND AVENUE TO 5TH AVENUE
EAST 75TH STREET, 1ST AVENUE T0~5TH AVENUE
CITY PROJECT N0. 618
WHREAS, it is proposed to improve the following area:
East 71st Street,
East 71st Street,
East 72nd Street,
East 73rd Street,
East 74th Street,
East 75th Street,
4th Avenue
3rd Avenue
3rd Avenue
3rd Avenue
2nd Avenue
1st Avenue
to
to
to
to
to
to
3rd Avenue
Stevens Avenue
Stevens Avenue
5th Avenue
5th Avenue
5th Avenue
by storm sewer construction and appurtenances thereto and to assess all property
benefitted for all or a portion of the cost of the improvement.
NOS;, THEREFORE, BE IT RESOLVED by the City Council of the City of Richfield,
Minnesota:
1. That the proposed improvement be referred to Orr-Schelen Mayeron &
Associates, Inc. (Consulting Engineers} for study and that they be instructed
to report to the Council with all convenient speed, advising the Council in a
preliminary way, as to whether the proposed improvement is feasible, the area
to be assessed, and as to whether it should best be made as proposed or in
connection with some other improvement and the estimated cost of the improvement
as recommended..
2. That the storm sewer improvement listed in this resolution shall hereafter
be known as City Project No. 618.
3. That the cost for preliminary work shall be paid from the Construction
Fund, such costs to be reimbursed when financing has been accomplished for the
construction of this project.
1970.
Adopted by the City Council of the City of Richfield this 23rd day of March,
c.,~. ~..~yt
MAYOR
C ATTEST:
CITY CLERK