04-18-88 agendaRICHFIELD HOUSING AND REDEVELOPMENT AUTHORITY
HRA Letter No. 18
Agenda April 18, 1988
Issue Statement:
Report on status of proposed Landmark Centre redevelopment
proposal.
®ackground•
At the February 1988 meeting, the HRA requested a status report
for Landmark Centre at each meeting. Last month a timetable was
presented (see attached copy).
For the April meeting, the developer will give an oral report
on the status of the development.
Decision Mode:
The HRA should consider the report by the developer and determine
if satisfactory progress is being made.
Respectfully submitted,
Jamb i~D . Prosser
Ex~cutive Director
JDP/eja
-}
. sy
T.R2dDNAR1C CENTER
pROPOBED TIISE BC'HEDULE
C02~PLET I ON
SECURE PURCHASE OPTIONS OF HO?~S
REVIEW VFiI RELOCATION ALTERNATIVES
CONDUCT ?IARICET ANALYSIS
SECURE PURCHASE OPTIONS OF COI4iERCIAL
SITES
PRE-LEASING INQUIRES
SECURE PURCHASE OPTION OF VFV
UPDATE DEVELOP?iENT CONCEPT AND PLANS
CONDUCT TRAFFIC STUDY
SUBIiZT AND RECEIVE HRA APPROVAL
NEGOTIATE AND OBTAIN DEVELOP?~NT/TIF
ecREEr~NT
VACATE STREETS A EASEl~NTS/R.EZONE/ETC.
OBTAIN FINANCING COlQIITIUrNT
PRE-LEASING
COIiPLETE DRAVINCS
PURCHASE VFV
PURCHASE HOBS i SUSZRESS PROPERTIES
DEKOLISH~EZISTING DUILDINGS
RELOCATE UTILI?IES
EZD/AVARD CONSTRUCTZON CONTRAC?S
COl~NCE fUILDING CONSTRUCTION
LEASING
3/1/88 S PEERS 4/1/88
3/1/88 6 QEERS 4/8/88
3/14/88 6 QEERS 4/22/88
3/14/8 8 6 VEERS 4/22/88
3/14/88 ONGOING
4/11/88 10 VEERS 6/17/88
5/2/88 10 VEERS 7/8/88
5/30/88 6 PEERS 7/8/88
7/8/88 2 VEERS 7/18/88
7/18/68 8 VEEY.S 4/9/88
8/8/88 8 PEERS 9/30/88
10/3/88 8 VEERS 12/2/88
7/11/88 OpGOZNG ----
9/12/88 10 VEERS 11/18/88
12/5/88 ---- ____
12/5/88 ---- ____
4/24/89 6 VEERS 6/2/89
5/8/89 6 VEERS 6/16/89
2/20/89 6 VEERS 3/31/89
5/1/89 78 PEERS 11/2/90
5/1/89 ONGOING ____
7
HOUSING AND REDEVELOPMENT AUTHORITY
HRA Letter No. 17
Agenda March 21, 1988
Issue Statement:
Review of developer's proposed time schedule for Landmark Centre.
Background•
At the meeting on February 16, 1988, the HRA authorized the newly
formed members of the Landmark Centre Partnership (Stuart and
Tushie) to proceed with staff toward the goal of negotiating a
developers agreement and initiating the construction of the
proposed development.
The HRA indicated, however, that they wanted to receive a report
at each monthly meeting on progress toward those goals.
On March 3, 1988 the developers and staff met to discuss the
appropriate way to proceed. It was concluded that staff and
developers would meet at least once a month. This is especially
appropriate during the early months because the developer is
responsible for many of the activities. Also, the developer
agreed to prepare a time schedule for presentation to staff and
the HRA.
Recommendation:
Review and comment upon the proposed time table and refer it to
staff for further analysis and possible refinement. A time
schedule incorporating HRA responsibilities with the proposed
schedule would then be provided the HRA.
Basis of Recommendation:
The HRA needs to have an understanding of the time estimates the
developer is projecting and to be comfortable with those
projections. Staff also needs an opportunity to review the
schedule with the developer and to review time estimates for
activities for which they are responsible.
Alternative Recommendation:
1) Reject the time table.
Decision Mode:
A timely response will facilitate the redevelopment process.
Respectfully submitted,
Jam D. Prosser
Exe tive Director
JDP:eja
^ ~ ~ Stuart Corporation
300 Shepazd Park Office Center
®. i 2177 Youngman Avenue
St. Paul, Minnesota 551163048
^ (612) 698-0302
j~~
March 11, 1488
Housing Redevelopment Authority
ATTN: Iir. Jim Prosser
City of Richfield
6700 Portland Avenue
Richfield, MN 55423
RE: LANDISARK CENTER PROPOSAL
LYNDALE AVENUE AND LAKE SHORE DRIVE
Dear Jim:
y_,
Stuart Corporation and Tushie Montgomery & Assoc., Inc. (Landmark Center
Partnership) extend their thanks to the City Staff and Housing Redevelopment
Authority (HRA) for having been selected to redevelop the northwest corner of
the Lyndale Avenue and Lake Shore Drive intersection in Richfield, MN.
This project offers some exciting prospects to continue the revitalization of
the Lyndale Avenue and 66th Street area.
Attached you will find a proposed time schedule outlining the activities
involved with completing the Landmark Center project.
The first steps include securing the necessary purchase options on all the
affected landowners located within the project area.. Concurrently, a formal
market analysis will be conducted along with independent pre-leasing inquiries,
all in an effort to confirm the most accurate picture of the market needs.
Also, we will assist the VFW in locating a site to build their new facility on.
Following the review of market conditions as revealed in the proposed market
analysis, Stuart Corporation will integrate any appropriate adjustments to the
original project scope and drawings..
We propose the HRA review the resulting final proposal and, if in favor,
recommend approval to consummate a development agreement and begin the processes
for all associated city approvals.
Based on the support of the city and our ability to resolve the purchase of
required land parcels and vacation of each business or resident., we hope. to
begin construction in the summer of 1989 with building completion and occupancy
in the fall of 1990
~~°~.
Mr. Jim Prosser
March 11, 1988
Page Two
Following your review of the proposed time schedule, we look forward to hearing
your comments.
Please call me at 698-0302 if you have any questions or comments.
Sincerely,
STUART CORPORATION
~`
Mark Houge
Commercial Real Estate Director
MH: jk
cc: Bruce Palmborg
Gary Tushie
Byron J. Wallace
~~~
LANDMARK CENTER
PROPOSED TIME SCHEDIILE
TAR DURATION COMPLETION
SECURE PURCHASE OPTIONS OF HOMES 3/1/88 5 WEEKS 4/1/88
REVIEW VFW RELOCATION ALTERNATIVES 3/1/88 6 WEEKS 4/8/88
CONDUCT MARKET ANALYSIS 3/14/88 b WEEKS 4/22/88
SECURE PURCHASE OPTIONS OF COMMERCIAL 3/14/88 b WEEKS 4/22/88
SITES
PRE-LEASING INQUIRES 3/14/88 ONGOING ____
SECURE PURCHASE OPTION OF VFW 4/11/88 10 WEEKS 6/17/88
UPDATE DEVELOPMENT CONCEPT AND PLANS 5/2/88 10 WEEKS 7/8/88
CONDUCT TRAFFIC STUDY 5/30/88 b WEEKS 7/8/88
SUBMIT AND RECEIVE HRA APPROVAL 7/8/88 2 WEEKS 7/28/88
NEGOTIATE AND OBTAIN DEVELOPMENT/TIF 7/18/88 8 WEEKS 9/9/88.
AGREEMENT
VACATE STREETS ~ EASEMENTS/REZONE/ETC. 8/8/88 8 WEEKS 9/30/88
OBTAIN FINANCING COMMITMENT 10/3/88 8 WEEKS 12/2/88
PRE-LEASING 7/11/88 ONGOING ____
COMPLETE DRAWINGS 9/12/88 10 WEEKS 11/18/88
PURCHASE VFW 12/5/88 ---- ____
PURCHASE HOMES ~ BUSINESS PROPERTIES 1Z/5/88 ---- ____
DEMOLISH E%ISTING BUILDINGS 4/24/89 6 WEEKS 6/2/89
RELOCATE UTILITIES 5/8/89 6 WEEKS 6/16/89
BID/AWARD CONSTRUCTION CONTRACTS 2/20/89 6 WEEKS .3/31/89
COMMENCE BIIILDING CONSTRUCTION 5/1/89 78 VEERS 11/2/90
LEASING 5/1/89 ONGOING ____
_- ~'
HOUSING AND REDEVELOPMENT AUTHORITY
HRA Letter No. 16
Agenda March 21, 1988
Issue Statement:
Authorization to extend Vo-Tech contract completion and payment
dates for property at 6514 Irving.
Background•
On August 17, 1987, the HRA authorized contracts with South
Hennepin Vocational Technical Center (Vo-Tech) to initiate two
projects for 1987-88.
A rehabilitation project was authorized for 6514 Irving Avenue
and a new construction project was authorized for 6632 Fifth
Avenue.
While the Fifth Avenue project is progressing on schedule, delays
in relocating a structure for rehabilitation at 6514 Irving
Avenue have altered the construction schedule for this project.
This letter requests that the contracts be modified to extend the
project completion and payment dates for the Irving project.
Relocation of the structure for rehabilitation was anticipated to
occur in early October, 1987.
Difficulties encountered in safely and successfully moving the 1-
1/2 story structure past utility lines, combined with delays on
the part of the moving contractor, postponed the house move until
February 23, 1988. Due to the delay, the Vo-Tech is unable to
meet the rehabilitation project completion date of August 1,
1988.
The Vo-Tech has submitted a revised construction schedule to
facilitate timely completion of the project. The present and
proposed completion dates are as follows:
Present Proposed
Completion Date Completion Date
August 1, 1988 November 30, 1988
A change in the completion date will also affect the date of
final payment for the contracted work.
The present and proposed dates of payment are as follows:
Present Proposed
Payment Date Payment Date
August 31, 1988 December 31, 1988
The new construction project authorized for Fifth Avenue will be
completed by November 1, 1988.
~~-~
Staff anticipates marketing both homes starting in June, 1988.
Vo-Tech is confident in their ability to meet the revised
schedule. (Vo-Tech is also confident that another new home can
be started on campus in the fall, 1988, and a new remodeling
project can occur in the spring, 1989. Lots at 619 East 70th
Street and 6840 Humboldt have already been purchased).
Recommendation:
Adopt the attached
1. A change in the
to November 30,
2. A change in the
to December 31,
resolution authorizing:
completion date for the Irving Ave. project
1988.
payment date of the Irving Ave. project
1988.
Basis for Recommendation:
1. Delays in the house move were beyond the control of Vo-Tech
and the HRA.
2. Revised construction schedules facilitate completion
of the project in a timely manner.
3. It is important that contract modifications be made now to
allow Vo-Tech to schedule curriculum activities in accordance
with the revised dates.
Alternative Recommendlation:
Do not authorize contract modification. However, the Vo-Tech
does not have the capacity to complete the project within the
original timeframe. Thus, the use of private contractors would
be required to complete construction. This would increase total
project costs and consume considerable time to switch from Vo-
Tech to a private contractor.
Decision Mode:
Contract changes, if acceptable to the HRA, will then be referred
to the school district for final action.
Respectfully submitted,
Ja D. Prosser
Ex utive Director
JDP:eja
~~
HRA RESOLUTION
Resolution For Amending Vo-Tech Construction Agreements
WHEREAS, the Housing and Redevelopment authority (HRA) in
and for the City of Richfield has entered into a contract with
South Hennepin Vocational Technical Centers (Vo-Tech); and
WHEREAS, a rehabilitation project was authorized for 6514
Irving Avenue South; and
WHEREAS, the HRA has determined that it is appropriate to
amend the construction agreement as it relates to the date of
completion and payment of work.
NOW, THEREFORE, BE IT RESOLVED by the Housing and
Redevelopment Authority in and for the City of Richfield,
Minnesota:
That the Chairperson and Executive Director are authorized
to execute contract amendments which:
1. Change the completion date for the Irving Ave. project;
to November 30, 1988.
2. Change the payment date for the Irving Ave. project;
to December 31, 1988.
Passed by the Housing and Redevelopment Authority in and for
the City of Richfield, this 21st day of March, 1988.
Thomas E. Harms, Chairperson
ATTEST:
Joan Helmberger, Secretary
~r~
HOUSING AND REDEVELOPMENT AUTHORITY
HRA Letter No. 15
Agenda March 21, 1988
Issue Statement:
Discussion of Local Strategy on Aging Task Force Recommendations.
Back round-
In December, 1987, the Local Strategy On Aging Task Force
completed a report entitled "Making Richfield Work For The
Elderly". The report is presently being distributed to the HRA
and Planning Commission. Earlier in March, the City Council and
Human Services Commission had an opportunity to review and
discuss the report. It has also been referred to the South
Hennepin Human Services Commission.
The report provides a summary of Task Force experiences since
1985, presents housing and service recommendations, and suggests
priorities for action. Commissioners Luettinger and Ludeman were
members of the task force.
This letter provides historical perspective. A presentation at
the March 21 HRA meeting will bring commissioners up to date.
Long term care issues are a national problem facing many cities.
It is not surprising to learn that. by the year 2000, Richfield
households, aged 75 or more, are projected to increase 146
percent and over 20 percent of the Richfield population will be
age 65 or older.
The dilemma is to determine what Richfield should do to improve
the existing housing and service system, eliminate gaps, and
assist elderly and all residents in maintaining a quality of
life.
For Richfield, the project started on May 20, 1985, with a
presentation to the HRA and Human Services Commission by Mrs.
Barbara Lukerman and the University of Minnesota Humphrey
Institute graduate students. The City Council and Planning
Commission also attended this meeting.
The presentation of "A Local Strategy On Aging-Richfield's
Opportunities" and the brainstorming that followed initiated
these events:
-The City Council established a Task Force with two
representatives from each of the following: City Council,
HRA, Planning Commission, and Human Services Commission.
-The Task Force began to meet regularly in January, 1986,
finalized a work plan in March, 1986, and met almost monthly
until the end of 1987.
~~1
The purpose of the Task Force has been to:
-understand the problems.
-identify alternatives, directions, opportunities, and
strategies.
-determine what are the desirable objectives of the city
concerning Richfield elderly and the housing and service
system.
-make recommendations to the City Council, Housing and
Redevelopment Authority, Planning Commission, and Human
Services Commission.
As was quickly discovered, the comprehensive demographic
information contained in the Lukerman study was only a portion of
the wealth of information that has been generated concerning
aging and long term care.
Five studies since 1982 provided direct information about
Richfield and the southern Hennepin County area. The resource
for this material included the Metropolitan Council, Humphrey
Institute, Hennepin County (both Community Services and the
Regional Park District), and South Hennepin Human Services.
This .initial resource of information identified existing
programs, the housing and service gaps in long term care, and
possible directions and strategies. The need for a larger
community role in assessment and service coordination was one
message that was often repeated.
The Task Force took this information as their foundation and
proceeded to meet with government officials, service providers,
consumers, and other professionals that come into contact with
Richfield programs and elderly.
With all of these resources, and assistance from staff, members
have been able to present their observations and discoveries in
the form of the report.
Some of the most valuable observations to the project and report,
to date, include:
-the ability of policy makers representing diverse interests
to collectively recognize the important housing and
service concerns.
-that Richfield is a great place to grow old, and many intend
to.
-in-home service is an increasingly critical component of
the long term care system. Information and referral,
transportation, in-home care, and case management are
elements of this component.
-affordable housing alternatives for fixed income/lower
income elderly is an ever present need.
~~~
Decision Mode:
The Council has referred the report to staff for further review
and discussion. Observations and discussion by each commission
is also being recorded to provide further. input.
Respectfully submitted,
Jame D. Prosser
Exec tive Director
JDP:eja