08-02-93 agendaCITY OF RICHFIELD
SPECIAL HOUSING AND REDEVELOPMENT AUTHORITY
MONDAY, AUGUST 2, 1993
7100 P.M.
COUNCIL CHAMBERS
AGENDA
CALL TO ORDER
I. REVIEW OF CONCURRENT USE OF SOUTH PART OF CLOVERLEAF SITE FOR
CONCRETE BATCH PLANT AND ROAD MATERIAL STORAGE AND RECYCLING
AREA FOR 77TH STREET PROJECT
HRA LETTER N0. 30
ADJOURNMENT
AUXILIARY AIDS FOR INDIVIDUALS WITH DISABILITIES ARE AVAILABLE
UPON REQUEST. REQUESTS MUST BE MADE AT LEAST 96 HOURS IN
ADVANCE TO THE ADMINISTRATIVE SERVICES DIRECTOR AT 861-9702.
HOUSING AND REDEVELOPMENT AUTHORITY
HRA Letter No. 30
Agenda August 2, 1993
Issue Statement:
Review of concurrent use of south part of Cloverleaf site for
concrete batch plant and road material storage and recycling area
for 77th Street Project.
Background:
On April 19, the HRA and City Council met concurrently. After
discussion, the HRA approved the use of the Cloverleaf site by
the 77th Street contractor for a concrete batch plant.
Shafer Contracting Co., Inc. has been selected as the 77th Street
contractor. The attached letter from Shafer relates a method of
operation which would stockpile concrete and asphalt to be ground
up for recycling as the new road base. In similar fashion, top
soil would be stockpiled for later utilization along 77th Street.
Based on the discussions at the April 19 meeting, the major
points of an agreement with Shafer are:
• permission to utilize the site for a batch plant and if
acceptable to the HRA the recycling of top soil asphalt and
concrete only as it relates to the 77th Street Project;
• before the batch plant may become operational, a portion of
the screenwall adjacent to the apartments on Emerson Avenue
must be constructed;
• if the batch plant won't be used for any 15 day consecutive
period, it must be removed;
• all operations on the Cloverleaf site must conform with the
noise ordinance;
• site taken "as is";
• HRA held harmless if there is a discharge of any hazardous
waste and contractor must remove;
• site to be restored to prior condition, $50,000 performance
bond to be provided;
• insurance in the minimum amount of $1 million for public
liability and a like amount for property damage;
• HRA indemnified and held harmless from any claims resulting
from use of site;
• operation must be conducted safely, liens against property
not permitted;
s agreement is for one year and may be extended, in writing,
for additional period and it may also be terminated
immediately for any significant breach of the agreement or by
90 day written notice for any other reason.
Recommended Motion:
Direct staff to include storage and recycling of road materials
in the agreement with the 77 Street contractor for the use of the
south part of the Cloverleaf site.
Basis of Recommendation:
1. Recycling helps to minimize costs.
2. The temporary storage of recyclable material can help to
reduce noise transmitted to adjoining property.
3. Storage at other locations would be more disruptive to the
neighbors and benefits of noise reduction lost.
Alternative Recommendation:
1. Do not approve use of site for recycling.
2. Delay action.
Discussion/Decision Mode:
A very early activity will be the removal of asphalt and
concrete. A site must be identified now as construction will
begin in days.
Resp t lly submitted,
Jame Prosser
Exec t ve Director
JDP:ds
~~~~
SHAPER, MINNESOTA 55074
July 23, 1993
Mr. Gary Orlich
BRW, Inc.
700 Third Street South
Minneapolis, Minnesota 55415
Re: S.P. 157-108-10
City of Richfield - 77th Street
Dear Mr. Orlich:
We are set to begin construction on this project. Among the first operations
will be salvaging topsoil for reuse in the final construction stages and the
removal of existing curb, gutter, sidewalk and pavement which we will salvage
and recycle for use as aggregate base.
We need to stockpile these materials, and we have several choices. One would
be to utilize the project right-of-way. The disadvantages of this are that
it will, to some extent, be in the way for construction, and also it will be
in close proximity to businesses and houses, and the recycling would affect
the residents more than the use of a more remote location.
I would propose that a better site for this stockpiling/recycling would be
the HRA property known as the Cloverleaf site. It is more removed from City
residents, and the closest property is the apartment complex which is some
distance away. We would arrange the stockpiles such that they would form a
noise mound barrier which will further minimize the effect of this construc-
tion activity. The cement batch plant would also be located on the property
during the fall concrete paving. During the concrete work, we would also use
material stockpiling to .act as noise mounds.
Our operations will be in accordance with all City. codes and regulations, as
well as the guidelines of the various State and Federal agencies on noise and
pollution.
We will control-dust by the use of water trucks. We will leave the site in as
good or better condition than exists today. This includes respreading of top-
soil, seeding and mulching. We would propose to furnish a surety bond in the.
amount of $50,000 to guarantee our restoration. of the site.